Context: The Cabinet Committee on Economic Affairs has approved continuation and revamping of the Scheme for Financial Support to Public Private Partnerships (PPPs) in Infrastructure Viability Gap Funding (VGF) Scheme Till 2024-25.

About the scheme: 

  • The Department of Economic Affairs, Ministry of Finance introduced the Scheme in 2006 with a view to support infrastructure projects undertaken through PPP mode that are economically justified but commercially viable due to large capital investment requirements.
  • VGF up to 40% of the Total Project Cost (TPC) is provided by the Government of India and the sponsoring authority in the form of capital grant at the stage of project construction (20%+20%).

Objectives of scheme:

  • The revamped Scheme is mainly for mainstreaming private participation in social infrastructure.
  • The aim of the scheme is to promote PPPs in social and Economic Infrastructure leading to efficient creation of assets and ensuring their proper Operation and Maintenance and make the economically/socially essential projects commercially viable. 

Components of scheme: There are two components of scheme namely:

  • Sub scheme -1
    • The Central Government will provide a maximum of 30% of Total Project Cost (TPC) of the project as VGF and State Government/Sponsoring Central Ministry/Statutory Entity may provide additional support up to 30% of TPC.
    • Eligibility: 
      • This is for Social Sectors projects such as Waste Water Treatment, Water Supply, Solid Waste Management, Health and Education sectors etc. 
      • These projects face bankability issues and poor revenue streams. 
      • The projects should have at least 100% Operational Cost recovery. 
  • Sub scheme -2
  • This Sub scheme will support demonstration/pilot social sectors projects
  • In such projects, the Central Government and the State Governments together will provide up to 80% of capital expenditure and upto 50% of Operation & Maintenance (O&M) costs for the first five years. 
  • Eligibility: The projects may be from Health and Education sectors where there is at least 50% Operational Cost recovery. 

Significance:

  • PPP projects: It will attract more PPP projects and facilitate private investment in the social sectors.
  • Employment and infrastructure: Creation of new hospitals, schools will create many opportunities to boost employment generation.

Viability Gap Funding (VGF) 

  • It means a grant one-time or deferred, provided to support infrastructure projects that are economically justified but fall short of financial viability. 
  • The lack of financial viability usually arises from long gestation periods and the inability to increase user charges to commercial levels. 
  • Through the provision of a catalytic grant assistance of the capital costs, several projects may become bankable and help mobilise private investment in infrastructure.

Public-Private Partnerships

  • Public-private partnerships involve collaboration between a government agency and a private-sector company.
  • It can be used to finance, build, and operate projects, such as public transportation networks, parks, and convention centers. 
  • Financing a project through a public-private partnership can allow a project to be completed sooner or make it a possibility in the first place. 
  • Public-private partnerships often involve concessions of tax or other operating revenue, protection from liability, or partial ownership rights over nominally public services and property to private sector, for-profit entities.

Imagesource: https://www.thalesgroup.com/

After reading this article, answer the following question for Mains answer writing practice. Also you can get your answer checked free of cost by clicking on the following link.

For Mains:https://www.jatinverma.org/home/typepost/dailymainsanswerwriting

Q) Critically discuss the pros and cons of the PPP model for infrastructure development of the country. (250 words)